A financial velocity metric calculated by dividing cumulative labor costs (from tracked time) by elapsed project duration, indicating how quickly a project is consuming its budget and enabling forecasting of budget exhaustion date, critical for early intervention when burn rate exceeds planned spending pace.
กำลังโหลด......
สำรวจรายการอื่นที่เกี่ยวข้อง
Burn Rate measures how fast a project consumes budget over time, providing early warning when spending pace exceeds projections and enabling corrective action before budget depletion.
Burn Rate = Total Costs Spent / Time Period
Example:
Runway = Remaining Budget / Burn Rate
Example:
Planned Burn Rate:
Comparison:
Green: Actual burn ≤ Planned burn Yellow: Actual burn 1.1-1.25× planned Red: Actual burn > 1.25× planned
Reduce Burn Rate:
Extend Budget:
Burn rate requires:
N/A - This is a project management metric.