Project planning technique using historical data from similar past projects to estimate duration and resource needs, leveraging organizational knowledge for more accurate time predictions.
더 불러오는 중......
Analogous estimation (also called top-down estimation) uses data from similar past projects to estimate the duration, effort, and resources needed for a new project.
Past Project: Website redesign, 3 developers, 4 months
New Project: Similar website redesign
Estimate: 4 months × (3/2 team ratio) × 1.2 (more features) = ~7 months