Project planning technique using historical data from similar past projects to estimate duration and resource needs, leveraging organizational knowledge for more accurate time predictions.
Зареждане на още......
Analogous estimation (also called top-down estimation) uses data from similar past projects to estimate the duration, effort, and resources needed for a new project.
Past Project: Website redesign, 3 developers, 4 months
New Project: Similar website redesign
Estimate: 4 months × (3/2 team ratio) × 1.2 (more features) = ~7 months